STA 1W Expansion No. 2, Palm Beach County, Florida; Provided cost estimating, scheduling, and constructability review services for the construction of this wetlands restoration project. This project includes 3 pump stations with a total capacity of 1745 CFS, approximately 10.5 miles of levee construction, and approximately 18 miles of canal excavation. [Estimated construction: $213M]
I-285 / I-20 West Interchange, Atlanta, GA; Provided cost estimating and scheduling services for this interchange reconfiguration project as part of the Major Mobility Investment Program. This project involves adding lanes along I-20, constructing collector-distributor lanes, and a complete reconstruction of the I-285/I-20 interchange including extensive flyover bridge construction. [Estimated construction: $640M]
C-23 to C-44 Interconnect, Martin County, Florida; Provided cost estimating and scheduling services for this Indian River Lagoon South project as part of the Comprehensive Everglades Restoration Plan. This project involves constructing a diversion from C-23 Canal to the C-44 Stormwater Treatment Area including a 250 CFS pump station, approximately 6.85 miles of canals, 2 box culverts at where the canal intersects existing roadways, a bridge, and a spillway. [Estimated construction: $55M]
Herat International Airport, Herat, Islamic Republic of Afghanistan; Led the cost estimating effort on this new international airport to be constructed in Herat, Afghanistan. The project includes a new airport terminal, combined airport services facility, pump house and generator building, fire water and water treatment facility, security watch tower, entry control point facility, and a switch gear facility. The site work includes airfield pavements, roadways and parking, and extensive utilities. [Estimated construction: $220M]
SR 400 Express Lanes, Atlanta, Georgia; Provided cost estimating and scheduling services for this GDOT project that is adding northbound and southbound express lanes and includes extensive bridge work through a 15-mile section of SR 400 in Atlanta, Georgia. This project also included bridge widenings over Big Creek and the Chattahoochee River. [Estimated construction: $900M] [With AECOM]
Miami Beach Monorail, Miami, FL; Provided cost estimating and advisory services for the construction of a monorail project between downtown Miami and Miami Beach along the MacArthur Causeway. This project includes 2 transit stations and approximately 3.5 miles of elevated monorail with a significant amount of over-water bridge construction. [Estimated construction: $573M] [With AECOM]
Wastewater Enterprise, SEO Islais Creek Crossing, San Francisco, California; Led the cost estimating effort for the replacement of existing 36” and 42” force mains across the Islais Creek Channel with two new 48” force mains. Due to environmental concerns and a challenging project location this project required 21 phases and extensive use of cofferdams. [Estimated construction: $67M] [With AECOM]
Homeland Defense Radar – Hawaii – Phase 1, Oahu, Hawaii; Provided cost estimate quality assurance services for the radar station, supporting missile defense command, and control components to be constructed at the Kuaokala Ridge. This project location is especially challenging given the uneven terrain and remote project location. [Estimated construction: Undisclosed] [With AECOM]
I-4 Connector, Tampa, Florida; Worked on the construction management team on this FDOT project which constructed an elevated tollway and connecting bridges between I-4 and the Selmon Expressway. This project included 12 precast post tensioned concrete segmental bridges made of nearly 2800 segments which were cast by the joint venture team. This project involved 1159 drilled shafts with some as large as 90”. There were also 11 concrete girder bridges, extensive MSE walls, the rerouting and lining of a canal, and construction of a Conspan bridge over a canal [Construction: $430M] [With Archer Western]
Mid Barataria Sediment Diversion, Louisiana; Provided cost estimate quality assurance services for the Mid Barataria Sediment Diversion Project. This project consists of concrete intake structures, gate structures, transition channels, railway relocations, road and bridge construction, conveyance channels and an outfall area. [Estimated total cost: $2B] [With AECOM]
NOTU Wastewater Treatment Plant, Cape Canaveral AFS, Florida; Provided cost estimating and scheduling services for the partial reconstruction of the Naval Ordnance Testing Unit's (NOTU) wastewater pre-treatment plant system. This project involved repairs and improvements as required at the Trident pre-treatment plant in facilities 62720-62735 at NOTU, Cape Canaveral Air Force Base (AFB), Florida. [Estimated construction: $6.5M] [With AECOM]
Tri-State Corridor (I-294) Mile Long Bridge, Chicago, Illinois; Provided cost estimating services for the replacement of the Mile Long Bridge between mile post 20.7 to mile post 22.3, crossing over the Des Plaines River, canals, and railways. Replacement of the bridges over La Grange Road is also included in this project. [Estimated construction: $1B] [With AECOM]
Munitions Storage Area, [Undisclosed Location], Europe; Provided cost estimating services for the construction of a munitions storage facility which includes 49 igloos, an administrative facility, an ammunitions and surveillance facility, a railway extension, various paved working areas, and site security and utilities. [Estimated construction: undisclosed] [With AECOM]
Water Control Structure #27 Refurbishment, Oakland Park, Florida; Led the cost estimating and value engineering effort on this refurbishment project of an existing water control structure. The project involved evaluating different spillway and culvert options to determine the most cost effective long-term solution for reconstructing this structure. [Estimated construction: $400K]
Raleigh St Improvements, Orlando, Florida; Provided cost estimating services for this roadway widening project for the City of Orlando. This project includes extensive roadway demolition and widening, full depth reclamation, a phased box culvert replacement, extensive storm drainage and sanitary sewer work, and the signalization of 2 intersections. [Estimated construction: $6.3M]
I-4 Beyond-the-Ultimate Segment 2, Orlando, Florida; Provided cost estimating and scheduling services for Segment 2 of the reconstruction of I-4 (known as the I-4 Beyond-the-Ultimate) in Central Florida. This project is expanding I-4 to include express lanes as well as reconfiguring intersections between Central Florida Expressway and Sand Lake Road. [Estimated construction: $800M] [With AECOM]
SR 528 Beachline Widening, Orlando, Florida; Worked on the construction management team on this Turnpike project which widened 4.28 miles of SR528 between I-4 and the Turnpike. The work included widening 6 overpass bridges, demolished and reconstructed a bridge over Shingle Creek, added 2 new bridges over John Young Parkway, added a toll facility, and added express lanes and auxiliary lanes in each direction. This project involved some very complicated traffic control phasing [Construction: $93M] [With Hubbard Construction Company]
SR 55/US 19 Reconstruction, Clearwater, Florida; Worked on the construction management team on this FDOT project which reconstructed 2.7 miles of the heavily travelled US19. The work included extensive utility relocations and new storm drainage, approximately 148,000SF of temporary walls and 253,000 of new MSE walls, and phased construction of 5 new bridges that involved concrete I-beams, concrete tub girders, and steel tub girders. [Construction: $132M] [With Hubbard Construction Company]